Lamledge Lane Primary School

Brief Job Description -

A local primary school based in Shifnal utilised our structures resulting in a cost effective and long lasting build.

Contract Period - 14 weeks / February - Aprill 2007

Job Weight - 75 Tonnes, Main Building, 25 Tonne Mechanical Workshop

Design - Full 2D CAD generated architectural drawings. - 3weeks

Manufacture - Inhouse manufacture and shipping - 7weeks

Contruction - Onsite erection and commission - 4weeks

More Pics: See Below
Foundations Complete
The Main Beams Are Connected
Completing The Main Structure..