Lamledge Lane Primary School |
![]() |
![]() |
|
Brief Job Description - A local primary school based in Shifnal utilised our structures resulting in a cost effective and long lasting build. Contract Period - 14 weeks / February - Aprill 2007 Job Weight - 75 Tonnes, Main Building, 25 Tonne Mechanical Workshop Design - Full 2D CAD generated architectural drawings. - 3weeks Manufacture - Inhouse manufacture and shipping - 7weeks Contruction - Onsite erection and commission - 4weeks |
| More Pics: See Below |
Foundations Complete |
The
Main Beams Are Connected |
Completing
The Main Structure.. |